The Hermitage Clinic – Linac Replacement Project
Taking place in a fully live and operational hopital this project required us to remove and replace the existing linac laser treatment unit, carry out a full fitout of the treatment rooms, control room and adjacent ancillary rooms. Full new floor, ceiling, and wall finishes were fitted throughout along with a deep M&E retro-fit to accommodate the new linac unit. There was also a lot of BWIC with M&E services which included crane lifts to the roof, construction of concrete plinths, and also multiple tracks, cuts and chases to accommodate the installation of the new unit. The project was completed on time and under budget.
Blackrock Health
Hermitage Clinic, Fonthill, Dublin 20
10 weeks
€510k
David Jordan Architects, Ascough Consulting Eng, Buildcost