DCU O’Reilly Library Refurbishment
This project consisted of two main areas of work. Internally we fitted out a large basement area with a large mobile book shelving/racking system and completed all associated fire upgrade works in the area while on the ground floor – we formed post graduate study rooms with 60min glazed partitions, new floor, ceiling and wall finishes. A full M&E re-fit was carried out on the affected rooms also.
Externally we carried out a complete re-roof of the entire roof area including all rooflights, rainwater outlets, flashings and upstands. This project was successfully delivered ahead of time and on budget.
Dublin City University
DCU Main Campus, Whitehall, Dublin 9
Dec 2020
5 Months
€780k
Moloney O'Beirne Architects, APNA QS, IN2 Partnership & OCSC Consulting