Kinnegad Medical Centre Fitout

Overview

As main contractor and PSCS, Murcom carried out the full internal fitout of a state of the Medical Centre, from an empty shell & core unit in Kinnegad town centre. The works consisted of the installation of 4 consultant medical suites, admin offices, reception and waiting areas, WC’s and canteen and tasked us with the installation of high end finishes, bespoke joinery, and considerable civil and drainage works. The use of colour added to the finished project allowing for a welcoming space for both patients and staff which we successfully delivered two weeks ahead of schedule.

CLIENT:

Private

LOCATION:

Kinnegad, Co. Westmeath

COMPLETION DATE:

Octoboer 2019

DURATION:

10 Weeks

VALUE:

€550k