TCD Category 2 Laboratory Fitout

Overview

Murcom were awarded this contract on the back of previous Laboratory fitout experience and duely delivered another category 2 fitout, this time for the Trinity College Bio-Science dept. This was a shell & core and fitout at -3 level where Murcom were the main contractor who co ordinated and supervised all construction, M & E and medical gas installation in a live educational building ensuring no disruption from noise or dust to students and staff.

CLIENT

TCD

LOCATION

Trinity Bio Science Building, Pearse St, Dublin 2.

COMPLETION DATE

September 2018

DURATION

12 Weeks

VALUE

€415k

DESIGN TEAM

FDA Consulting, Ascough Consulting Engineers